Council is upgrading areas along Russell Street, Coburg. The project aims to revitalise the area and improve the pedestrian amenity, walkability and presentation of the street. This project is a key action from the Coburg Streetscape Masterplan identified for implementation in 5 - 10 years.

Construction is anticipated to commence in January 2020 (subject to VicRoads approval) and complete by October 2020. The extents of works is shown overleaf on the Concept Plan. During construction, access will be maintained to all properties in the works area. Council will make every effort to minimise disruption to the adjoining businesses and residents.

 

Final Design Plan

final design

 Final Design Plan (PDF 4Mb)

 

Consultation – Have your say

Feedback received from the community consultation in March 2019 informed the development of the Draft Concept Plan to address various issues including safety, amenity, connections and the presentation of the public area. The summary of the consultation findings can be downloaded here:  Summary of consultation survey (PDF 172Kb).

 Russell Street Precinct

 

Budget and timelines

  • Budget for design: $50,000, design completion: June 2019
  • Budget for construction TBA (to be advised), construction completion: October 2020

More information

If you have any queries regarding the project, contact Council’s Council’s Urban Designer, Ben Kazacos on 9240 1287 or email Ben Kazacos.

 

Construction is anticipated to commence in January 2020 (subject to VicRoads approval) and complete by October 2020. The extent of works is shown overleaf on the Concept Plan. During construction, access will be maintained to all properties in the works area. Council will make every effort to minimise disruption to the adjoining businesses and residents.