Council has upgraded the existing public toilet in line with the Public Toilet Strategy 2012 (revision February 2016) Appendix D – Capital Works implementation program.

The works comprised:

  • Demolition of the existing old toilet block 
  • Construction of a new 1D unisex accessible public toilet in the same location as the existing public toilet, and
  • Construction of an accessible concrete path that joins the existing path network.

The new toilet facility is controlled by a solar powered locking system and open during daylight hours only.

Program timelines

  • Construction start date: February 2018
  • Construction end date: May 2018

Budget

$69,000