Spry Street, Coburg North – Road reconstruction works

Spry Street CoburgProject overview

In 2016-17 Council reconstructed Spry Street, Coburg North on the east side of Sydney Road.

The works comprised:

  • Construction of a new underground drainage system and pits.
  • Reconstructing the existing concrete kerb and channel. The levels will be altered to flatten the road and improve vehicle access into properties.
  • Laying a new asphalt road surface.
  • Reconstruction of vehicle crossings between the new kerb and footpath edge.
  • Reinstatement of nature strips.
  • Total length: 375 m

Budget and timelines

  • Total Project Cost: $507,413
  • Construction start date: September 2016
  • Construction end date: December 2016