Crozier Street, Coburg – Road reconstruction works

Project overviewCrozier Street - Before road reconstruction works

In 2016/17 Council will be reconstructing Crozier Street, Coburg between Nicholson Street and Cole Crescent.

Consultation with residents was undertaken in August 2016.

The project is in the tender phase, with works set to commence in April 2017.

The works will comprise:

  • Construction of a new underground drainage system and pits.
  • Reconstructing the existing concrete kerb and channel. The levels will be altered to flatten the road and improve vehicle access into properties.
  • Laying a new asphalt road surface.
  • Reconstruction of vehicle crossings between the new kerb and footpath edge.
  • Reinstatement of nature strips.
  • Total Length: 255 m

Budget and timelines

  • Budget: $454,000.
  • Construction start date: April 2017
  • Construction end date: June 2017