Coburg Street, Coburg – Road reconstruction works

Coburg Street - Before Road Reconstructions WorksProject overview

Council will be reconstructing Coburg Street, Coburg between Rennie Street and Walsh Street.

Consultation with residents was undertaken in August 2016.

The project is in the Construction phase, with works commencing in September 2017.

The works will comprise:

  • Construction of a new underground drainage system and pits.
  • Reconstructing the existing concrete kerb and channel. The levels will be altered to flatten the road and improve vehicle access into properties.
  • Laying a new asphalt road surface.
  • Reconstruction of vehicle crossings between the new kerb and footpath edge.
  • Reinstatement of nature strips.
  • Total Length: 260 m

Budget and timelines

  • Budget: $623,000
  • Construction start date: September 2017
  • Construction end date: March 2018