Dunnes Lane, Coburg pedestrian link

Dunnes LaneProject overview

Council has recently upgraded Dunnes Lane in Coburg. The purpose of this project was to improve the laneway's pedestrian accessibility and presentation.  

Budget and timelines

  • Budget: Council funding $200,000 plus Melbourne Water Grant $42,500
  • Construction start date: April 2016

Major stages of the project

Consultation - complete

Consultation for this project finished in September 2015. 

Design - complete

From the feedback Council received during the consultation process, a final design for Dunnes Lane was developed.

For more information, refer to the Concept Design (PDF 4Mb).

Dunnes lane, Coburg    Dunnes lane, Coburg

Tendering - complete

Public tender for the construction work was advertised over November - December 2015.

Construction - complete

Construction was completed in August 2016. 