Coburg City Oval

Project overview

City Oval footpath and fence rear of pavilion

The Draft Coburg City Oval Landscape Plan is the first stage of the Coburg City Oval Redevelopment and is expected to be completed by June 2015.

Stage 1 Landscaping will open up Coburg City Oval for greater community access and future stages of City Oval Redevelopment will see improvements all around oval to improve access, increase amenity and recreation opportunities within the precinct. Draft Coburg City Oval Precinct Landscape Master Plan (PDF 1Mb) shows proposed future improvements all around oval

Stage 1 of the Coburg City Oval Redevelopment proposes a newly landscaped western edge that opens up access the oval with the installation of operable fencing and gates. This will improve circulation and connectivity while preserving the capacity of the oval for holding ticketed events. This is shown in the Draft Coburg City Oval Stage 1 Landscape Plan (PDF 831Kb).

Images of how the completed project will look can be seen in the Draft Coburg Oval Stage 1 Artist Perspective and Elevation (PDF 1Mb).

Major stages of the project

Consultation

Council  prepared a Draft Coburg City Oval Precinct Landscape Master Plan (PDF 1Mb) to improve community access to this open space in Coburg, which was available for comment in December 2014.

There are documents on this page in PDF-only format. If you have trouble opening or viewing a PDF document, contact Council and we will arrange to provide the information in a format that suits your needs. See Council's accessibility page for further details.

Construction

City Oval construction work

Early works began on site at the City Oval in April 2015, with removal of low quality vegetation across the western face of the sports ground and gravel paving from the rear of the Bowls Club up to the ticket entry to the Oval. At this time the opportunity was taken to carry out formative pruning of the two large Gum trees that have been retained in this vicinity.

By end of June 2015, these works had given a face lift to the Oval that includes the installation of new charcoal mesh fencing to the rear of the pavilion and other buildings on the western boundary along with improved pedestrian access with the creation of a footpath along the edge of the Russell Street carpark.

While these improvement works were progressing detailed documentation was being finalised for procurement, resulting in appointment of contractors for fabrication and installation of heavy steel operable fencing, extensive new concrete paving and spectator terracing along with associated earthworks and in-ground services.

By November 2015, practical completion of all civil works was achieved and landscaping works underway for provision of the final surface finishes and planting.

Irrigation works to the oval have been ongoing since March, with works expected to be completed by May 2016. The net project will begin in May 2016 and aim to be completed by June 2016.

The oval will be open to general public by July 2016. All of the gates on the western edge will be in the open position once the Oval is in a safe condition for public access.

These and all of the existing gates around the park perimeter will be in the closed position on match days (or other ticketed events) apart from ticket booth gate(s).

The oval will be open to general public by July 2016. All of the gates on the western edge will be in the open position once the Oval is in a safe condition for public access. These and all of the existing gates around the park perimeter will be in the closed position on match days (or other ticketed events) apart from the single ticket booth gate.

 